Progress on annual parking works management plan 2022-23

Quarter 1

Project Title Start Date Project Status
Whitton Road / Argyle Avenue - Time limited bays June 2021 Complete
Basildene Road - Time limited bays June 2021 Complete

 

Quarter 2

Project Title Start Date Project Status
Ellerdine Road area integration into RFU CPZ April 2018 Complete
Hanworth Road, Hounslow - waiting, loading and footpath parking June 2020 Complete
Spencer Road CPZ review January 2021 Complete
Osterley Leisure Centre Car Park April 2021 Complete
Thornberry Avenue area full CPZ review November 2021 Complete

 

Quarter 3

Project Title Start Date Project Status
Catherine Gardens November 2021 Complete
Disabled bay applications (inc. consolidation order) N/A Ongoing
Staines Road - Cassiobury Road and Bedfont Lane December 2021 Complete
Ridgeway Road CPZ review September 2021 Complete
Sherbourne Road - removal of DYL November 2021 Complete
Staines Road (Hounslow Heath) pay and display controls November 2021 Complete

 

rating button