Quarter 1
Project Title | Start Date | Project Status |
---|---|---|
Whitton Road / Argyle Avenue - Time limited bays | June 2021 | Complete |
Basildene Road - Time limited bays | June 2021 | Complete |
Quarter 2
Project Title | Start Date | Project Status |
---|---|---|
Ellerdine Road area integration into RFU CPZ | April 2018 | Complete |
Hanworth Road, Hounslow - waiting, loading and footpath parking | June 2020 | Complete |
Spencer Road CPZ review | January 2021 | Complete |
Osterley Leisure Centre Car Park | April 2021 | Complete |
Thornberry Avenue area full CPZ review | November 2021 | Complete |
Quarter 3
Project Title | Start Date | Project Status |
---|---|---|
Catherine Gardens | November 2021 | Complete |
Disabled bay applications (inc. consolidation order) | N/A | Ongoing |
Staines Road - Cassiobury Road and Bedfont Lane | December 2021 | Complete |
Ridgeway Road CPZ review | September 2021 | Complete |
Sherbourne Road - removal of DYL | November 2021 | Complete |
Staines Road (Hounslow Heath) pay and display controls | November 2021 | Complete |