Highway Maintenance Works

Additional Resurfacing and Highways Maintenance work 2024

The London Borough of Hounslow is pleased to have received extra funding from the Department for Transport which was unlocked and made possible by reallocated HS2 funding.   

The PFI, delivered by Hounslow Highways, has published their Major Maintenance programme for 2024 and this funding has allowed us to plan in treatment on roads where no treatment would have occurred, either in full or repair, as per the latest Independent Surveys carried out in mid-2023. 

The Council has selected a number of roads or sections of roads where this fund will be applied.  We’ve assessed data and asset information and can confirm the following roads and sections will be treated using this funding. 

Thi is a standalone programme of works and in addition to any schemes being completed by Hounslow Highways as part of the PFI.  Details of the work being carried out within the PFI can be found on the Hounslow Highways website.

The programme has been finalised with the below dates of works.  All affected residents will be written to in advance of the works beginning. 

ROAD NAME 

EXTENT 

WARD 

DATE OF WORKS 

SPARROW FARM DRIVE

CYGNET AV TO JCT DURHAM RD

FELTHAM NORTH

11 November 

ARMYTAGE ROAD 

CRANFORD LN TO ALCOCK RD 

HESTON WEST 

7- 8 October

WINSLOW WAY 

HOUNSLOW RD TO END OF RD 

HANWORTH 

4 - 6 November  

LAMPTON AVENUE 

LAMPTON RD TO END OF RD  

HESTON EAST 

28 - 30 October 

CLIFDEN ROAD 

BROOK RD S TO WINDMILL RD

BRENTFORD 

31 October –  

2 November 

WINDMILL ROAD 

CHISWICK HIGH RD TO END OF RD

CHISWICK GUNNERSBURY 

21 - 22 October 

BRABAZON ROAD 

BRABAZON RD T JCT TO COBHAM RD

HESTON WEST 

24 October

MYRTLE AVENUE 

HATTON RD TO END OF RD 

BEDFONT 

23 October

 

Funded by UK Government and Levelling Up

 

 