Additional Resurfacing and Highways Maintenance work 2024
The London Borough of Hounslow is pleased to have received extra funding from the Department for Transport which was unlocked and made possible by reallocated HS2 funding.
The PFI, delivered by Hounslow Highways, has published their Major Maintenance programme for 2024 and this funding has allowed us to plan in treatment on roads where no treatment would have occurred, either in full or repair, as per the latest Independent Surveys carried out in mid-2023.
The Council has selected a number of roads or sections of roads where this fund will be applied. We’ve assessed data and asset information and can confirm the following roads and sections will be treated using this funding.
Thi is a standalone programme of works and in addition to any schemes being completed by Hounslow Highways as part of the PFI. Details of the work being carried out within the PFI can be found on the Hounslow Highways website.
The programme has been finalised with the below dates of works. All affected residents will be written to in advance of the works beginning.
ROAD NAME |
EXTENT |
WARD |
DATE OF WORKS |
SPARROW FARM DRIVE |
CYGNET AV TO JCT DURHAM RD |
FELTHAM NORTH |
11 November |
ARMYTAGE ROAD |
CRANFORD LN TO ALCOCK RD |
HESTON WEST |
7- 8 October |
WINSLOW WAY |
HOUNSLOW RD TO END OF RD |
HANWORTH |
4 - 6 November |
LAMPTON AVENUE |
LAMPTON RD TO END OF RD |
HESTON EAST |
28 - 30 October |
CLIFDEN ROAD |
BROOK RD S TO WINDMILL RD |
BRENTFORD |
31 October – 2 November |
WINDMILL ROAD |
CHISWICK HIGH RD TO END OF RD |
CHISWICK GUNNERSBURY |
21 - 22 October |
BRABAZON ROAD |
BRABAZON RD T JCT TO COBHAM RD |
HESTON WEST |
24 October |
MYRTLE AVENUE |
HATTON RD TO END OF RD |
BEDFONT |
23 October |