Watermans Park development
Read how we're improving Waterman’s Park for residents and why the temporary closures are in place.
We are fortunate to have wonderful parks and open spaces in Hounslow and during the pandemic, more than ever, it became evident just how much you value them. We know that investment in our parks and open spaces is one of our key priorities as these spaces are a vital way of supporting the health and wellbeing of the community.
Watermans Park is an important asset for local residents who use the park for lots of different recreational activities. It is also a valuable green space to help tackle the current nature and climate change emergency. There are planned developments on site that are giving us an opportunity to develop the park and improve the infrastructure.
Residents were recently given the opportunity to share their thoughts via a questionnaire on the value of the park and the play area and suggest improvements. This has helped us to develop our plans for the park improvements based on the community need and to develop this green space as a great community hub.
A summary for the survey can be found here
We also engaged with local school children from Green Dragon Primary School and St Paul’s CE Primary School who shared their design visions for the play area.
View Watermans Park masterplan
Watermans Park Improvements Update - 1 February 2022
New Pedestrian Paths and Cycleway
All new cycleway and footpaths installed including edges and base course. Pergolas installed. Final wearing course to paths planned during March.
All new cycleway and footpaths installed including edges and base course. Pergolas installed. Final wearing course to paths planned during March.
Cycle path and pedestrian path retaining wall and ramp to form new access at the eastern end of the site complete.
New Seating Areas
All new seating areas and pergolas installed. Seats due to arrive on site 2 February 2022. Resin bound paving under seating planned during March
New play area and equipment
New play area, basketball area, fencing and equipment all installed. Safety surfacing to be installed in March.
Tree and shrub planting
All Extra Heavy Standard (EHS) trees on site and are currently being planted. Completion of EHS planting expected end of the week.
Bare root stock and shrub planting expected late February.
Update following site visit 08th March 2022
1. New Pedestrian Paths, Pergolas, Seating and Cycleway
1.1 All new footpaths installed including edges and base course. Pergolas installed. Some remedial works to paths carried out following comments from Friends.
New pedestrian paths, pergolas, seating and wildflower turf
1.2 Cycle path and pedestrian path retaining wall and ramp to form new access at the eastern end of the site complete. Note: Delay with lighting columns from manufacturer cycle path opening will be delayed due to long lead in time from Scottish Power.
New pedestrian cycle and pedestrian entrance
2.0 New social space
2.1 New social space complete including resin paving, picnic tables and table tennis tables. Awaiting confirmation from Friends about Library depository.
New Social Space
3.0 New play area and equipment
3.1 New play area, outdoor gym, basketball area, fencing and all equipment including safer surfacing installed.
New play area
4.0 Outdoor yoga
4.1 Outdoor yoga space complete
Outdoor Yoga area
5.0 Tree and shrub planting
5.1 All Extra Heavy Standard (EHS) planting, native planting, and herbaceous planting complete. Ceremonial Planting took place11th March 2022. Storm damaged fallen tree replaced.
Planting complete
allen tree from storm damage replaced as above
6.0 Cycle racks and friends information board
Cycle stands and moving Friends Information Board complete.
Entrance and cycle stand
6.0 Other works
6.1 Boardwalk. New structural survey to take place end of March. Once results known can proceed.
6.2 Cycle way demarcation kerbs and lighting columns to be installed end of the month. Power connections waiting for Scottish Power.
6.3 Install irrigation points and drinking fountain. To be completed May – waiting for Thames Water
6.4 Community planting day to be agreed.
Completion date 31 March 2022 will be achieved.
Boardwalk improvements at Watermans Park - Update 17 March 2022
Hounslow Council and its partners are working hard on the improvement plan for Watermans Park.
An important part of the transformation will be to bring the boardwalk that runs along the River Thames back into use.,
This work is progressing and we are currently undertaking surveys, which will determine the extent of the work needed to bring the boardwalk back into use. To complete any future work, we will need access to the boardwalk from the park and the river. This means that the timetable will be dictated by the tidal nature of the Thames.
For this reason, work will continue on the boardwalk improvements after the main park improvements are finished and the park has re-opened.
We will keep you informed of developments on this important project and provide timescales for the work as the plan develops.